DETROIT WATER AND SEWERAGE DEPARTMENT

ROMEO ARM OF THE MACOMB SEWER INTERCEPTOR


December 6, 2004 Update

One hundred-eight of 240 caissons have been installed in the sinkhole around the repair area. The caissons are being installed to a depth
of 65-feet.

Crews are excavating down to the interceptor. The excavation started east of the area to be repaired. So far, an area 70-feet long by 40-feet wide and 30-feet deep has been excavated.

DWSD is making every effort to minimize the noise impact on the surrounding area while installing the caissons.




Click images for larger versions
Images upated December 3,2004


back to Macomb Interceptor Information
 

Please direct your comments or questions regarding this site to the Public Affairs Division at (313) 964-9460 or e-mail us.
All content, artwork, and information included herein is ©2007 Detroit Water & Sewerage Department
Home, Customer Info, About DWSD, Announcements, Projects, Facilities, History, Procurement, Links