DETROIT WATER AND SEWERAGE DEPARTMENT
ROMEO ARM OF THE MACOMB SEWER INTERCEPTOR
November 19, 2004 Update
On Sunday, November 14th, crews completed the installation of the second steel bulkhead located to the west of the repair area, and are removing a mixture of sand and sludge from the interceptor.
Sixty-nine of 240 caissons have been installed in the sinkhole around the repair area. The caissons are being installed to a depth of 65-feet. Crews expect to have enough caissons in the sinkhole by Tuesday, November 23rd to start excavating down to the interceptor. The excavation will start from the east and go west.
DWSD is making every effort to minimize the noise impact on the surrounding area while installing the caissons.
Click image for a larger version
back to Macomb Interceptor Information
|
|
|
Please direct your comments or questions regarding this site to the Public Affairs Division at (313) 964-9460 or e-mail us.
All content, artwork, and information included herein is ©2007 Detroit Water
& Sewerage Department
Home, Customer Info, About DWSD, Announcements,
Projects, Facilities, History, Procurement,
Links |