Work is continuing on installing the second steel bulkhead located to the west of the repair area. The bulkhead is approximately 40-percent done and is expected to be completed by mid-November.

Crews are removing a mixture of sand and sludge from the portion of the interceptor to be repaired.

Augers have drilled 39 holes for caissons. A total of 250 caissons will be installed in the sinkhole around the repair area. The caissons are being installed to a depth of 65-feet.

DWSD is making every effort to minimize the noise impact on the surrounding area while installing the caissons.


Click image for a larger version


back to Macomb Interceptor Information
 

Please direct your comments or questions regarding this site to the Public Affairs Division at (313) 964-9460 or e-mail us.
All content, artwork, and information included herein is ©2007 Detroit Water & Sewerage Department
Home, Customer Info, About DWSD, Announcements, Projects, Facilities, History, Procurement, Links