DETROIT WATER AND SEWERAGE DEPARTMENT
ROMEO ARM OF THE MACOMB SEWER INTERCEPTOR
September 22, 2004 Update
Divers have completed cleaning operations, removing the steel and wood lagging boards, in suction shafts 1 and 2. Holes have been cut into the top of the interceptor’s concrete wall, creating an opening at the bottom of each shaft. Each suction shaft will have 2 bypass pumps. The pumps are being installed approximately 10 and 20–feet above the interceptor.
Divers have also completed the cleaning operations in the discharge shaft and cut through the top of the interceptor.
Crews are installing trench boxes where the two 36-inch bypasses will be located below ground level. The trench boxes shore the sides of the trench for workers’ safety. The bypass pipes will be attached to the pumps through wall of the suctions shafts.
Twelve dewatering wells are now in service to remove ground water from around the site.
Click image for a larger version
back to Macomb Interceptor Information
|
|
|
Please direct your comments or questions regarding this site to the Public Affairs Division at (313) 964-9460 or e-mail us.
All content, artwork, and information included herein is ©2007 Detroit Water
& Sewerage Department
Home, Customer Info, About DWSD, Announcements,
Projects, Facilities, History, Procurement,
Links |