Excavation of the approximate 240-foot damaged section of the interceptor has been completed. Crews are continuing preparing and installing new pipe. Five pipe sections (8-feet long, 11-feet in diameter) have been installed and 84-feet of mudmat. Crews are in the process of placing 4 more sections in the trench at the east end of the repair area. Crews will continue with replacement sections moving westward along 15 Mile Road.
To replace the damaged portion of the interceptor, crews must remove the top portion of the collapsed interceptor and place a concrete mudmat on top of what’s left of the collapsed section. Once the mudmat is in place, holes will be drilled down into the remaining interceptor. Grouting will be inserted to totally fill every cavity left in the damaged section, forming a solid support base. Next, a steel and concrete cradle will be installed on top of the mudmat to support the new pipe being installed.
Click images for larger versions
Images upated December 3,2004
back to Macomb Interceptor Information
|
|
|
Please direct your comments or questions regarding this site to the Public Affairs Division at (313) 964-9460 or e-mail us.
All content, artwork, and information included herein is ©2009 Detroit Water and Sewerage Department
Home, Customer Info, About DWSD, Announcements,
Projects, Facilities, History, Procurement,
Links |